Home

Posted on: July 31, 2017

2017 Pavement Rehabilitation Program

sundown terrace 2

Raising of existing utilities back to top of newly paved roadways will continue through October. The replacement roadway striping installation has begun for locations on the south side of Highway 24. The remaining streets north of Highway 24 will be striped in early November. All pulverizing, roadway grading and cement treating work is now complete for the project.

New HMA paving completed this week at the following locations:

  • Sundown Terrace
  • Redcoach Lane
  • Candle Terrace
  • Upper & Lower Van Ripper Lane
  • Sunnyside Court

The final road repair at El Nido Ranch Road will consist of milling/grinding the existing roadway to a 3-inch depth and repaving, with a possibility of additional, deeper repairs in isolated locations. 

Storm drain pipe and concrete ditch/curb/gutter replacement work is now complete on the project, but there will be miscellaneous follow up work to fix or improve minor issues throughout the project in October.

New asphalt curb & gutter layout work is complete, installation is scheduled to start the week of October 16, 2017 with all locations, north & south of Highway 24, estimated to be installed within a one-week time frame. Related asphalt lined ditches are underway with grading work starting this week and continuing into the next two weeks with the asphalt work following close behind. Follow-up completion efforts, corrective work & damage repair work throughout the project will be started next week and run through the month of October. Total project completion is estimated to be November 17, 2017.

Read More
Facebook Twitter Google Plus Email

Other News in Home

Streetfeast3

Food Truck Thursdays!

Posted on: August 8, 2017
STR_pic

Short Term Rentals

Posted on: August 24, 2017